Partners Group agrees to acquire atNorth for Nordic expansion

The December 2021 agreement combined Icelandic operations with a Stockholm site under construction. Financial terms were undisclosed.

RAFT editorial illustration: Operating and developing data-centre capacity in a Nordic landscape.
Conceptual Nordic data-centre campus, combining operating facilities and construction. Not a depiction of an atNorth property. RAFT editorial illustration

Partners Group agreed on behalf of clients to acquire atNorth from its shareholders on 21 December 2021. The announcement disclosed no price and set out plans to expand the operator across the Nordics.

RAFT Analysis

Partners Group’s atNorth agreement combined an income-producing Icelandic business with the funding and leasing demands of Nordic expansion.

The December 2021 announcement described two Iceland locations with about 83 MW of committed power and an approximately 11 MW Stockholm site under construction. The operating sites could support expansion, while the Stockholm project required delivery and customer commitments before generating its full income.

In June 2021, Landsvirkjun and Verne Global announced a power contract running to 2030. Longer power-price visibility can make colocation margins easier to underwrite, but atNorth’s own tariff, contract length and customer pass-through terms still required diligence.

Landsvirkjun said the Verne agreement supplied renewable electricity and offered long-term visibility on energy costs. Renewable supply could help win compute customers, while investment returns still depended on the spread between customer receipts, electricity costs and the capital spent fitting out capacity.

Verne’s contract offered a contemporary example of long-term power procurement in the same market. Verne’s agreement concerns another Icelandic operator and establishes no equivalent contract or tariff for atNorth.

The purchase price and atNorth’s power-contract economics were undisclosed. Committed MW cannot establish occupied capacity, revenue or value per MW. The investment test was how quickly committed power became commissioned capacity with paying customers, and how much capital that conversion consumed.

Sources