From the archive · December 2023

Digital Realty and Blackstone agree $7bn data-centre development JV

The December 2023 agreement paired private capital with a multi-year pipeline in Frankfurt, Paris and Northern Virginia.

Historic photograph of Frankfurt’s city-centre skyline, provided as geographic context.
Historic Frankfurt skyline, shown for city context. This photograph does not depict a JV campus. Carlos Delgado; CC BY-SA 3.0 · CC BY-SA 3.0

On 7 December 2023, Blackstone-affiliated funds and Digital Realty agreed to develop four data-centre campuses across Frankfurt, Paris and Northern Virginia. The programme had an estimated $7bn development cost and 500 MW of potential IT capacity. Blackstone proposed an initial $700m contribution for an 80% stake. Digital Realty would retain 20%.

Of the planned capacity, 46 MW was under construction and 33% of that phase was pre-let. The partners expected two-stage closing in the first half of 2024, subject to conditions. The $7bn figure described estimated development cost over several years; it was separate from initial equity.

RAFT Analysis

Blackstone’s proposed partnership gave Digital Realty capital to develop a multi-year pipeline, with a larger leasing task than the operator’s fully pre-let Realty Income venture announced a month earlier.

After closing, Blackstone and Digital Realty were to fund remaining development costs in proportion to their 80% and 20% stakes, while Digital Realty earned development and operating fees. Digital Realty would retain a minority share of the capital requirement and a fee income stream, while Blackstone supplied most of the partner equity.

Digital Realty’s 13 November 2023 Realty Income JV covered two Northern Virginia facilities that were fully pre-let before construction, with 16 MW of initial capacity and expansion up to 48 MW at the customer’s option. Against that contracted build-to-suit model, the Blackstone programme needed more customer commitments before its construction pipeline could provide comparable income visibility.

CBRE’s July 2023 report put Frankfurt colocation vacancy at 4.8% in Q1 2023, down from 8.6% a year earlier. Scarce operating space supported the case for new capacity in Frankfurt, but the partners still had to secure power and complete construction before they could earn rent from that demand.

CBRE’s July report identified power availability and construction delays as constraints on new data-centre supply. A tight occupier market could help the venture sign customers, while delayed grid connections could defer income despite committed investor capital.

The same operator had just paired private capital with fully contracted customer demand in Northern Virginia; the Blackstone JV had only 33% of its 46 MW construction phase pre-let. The comparison is between leasing structures, not yields: two customer-led US facilities differ from four campuses spanning three metros, and 33% applies only to the Blackstone JV’s 46 MW construction phase. Frankfurt was one of the Blackstone JV’s target metros, so limited vacant operating capacity supported its development rationale. This is an earlier citywide measure of operating wholesale and retail colocation capacity, not a December vacancy estimate or a leasing forecast for the four-campus JV.

Low Frankfurt vacancy offered a plausible route to faster pre-letting. That opportunity depended on delivering powered space when customers needed it, rather than on capital availability alone. At announcement, the next milestones were the proposed 2024 closings and further customer commitments for the 46 MW construction phase. The agreement and announced timetable do not establish completion or delivered capacity.